A project can be said to be successful, one of which if there is no accident or zero accident in the project. Occupational health and safety (OHS) is one of the crucial factors for the success of a construction project. As stipulated in the Peraturan Menteri Pekerjaan Umum Nomor : 05 / PRT / M / 201 concerning about general SMK3 provisions that must be applied by contractors and for Surat Edaran Menteri Nomor : 66 / SE / M / 2015 regarding the provisions on the cost of applying SMK3 in project construction. Therefore, the purpose of this study is to evaluate implementation of OHS in the Bendo – Ponorogo dam project and to determine the percentage of the cost of implementing OHS in project. Data collection methods used for this study are twofold, firstly primary data is data from interviews and second is secondary data is data from the contractor. The results of this study indicate that the application of OHS already implemented but not maximum yet and the allocation of SMK3 costs taken by the contractor is 0.27% of the contract cost and for PEE needs only constructed Main Dam is Rp. 106,090,00.00.
A project can be said to be successful, one of which if there is no accident or zero accident in the project. Occupational health and safety (K3) is one of the crucial factors for the success of a construction project. In today's world things like safety are often overlooked because they are considered to be a waste of time and money. Therefore it is necessary to control and Work Safety Cost Planning in Construction Projects. Construction work on buildings is work that is dense with activities with a high level of risk, especially in large project projects such as the Bendo - Ponorogo dam construction project (Multiyear). Construction work is work involving engineering consultants as planners, contractors as executors and supervisory consultants, all of these elements, both planners, contractors and supervisors, have their own contribution to the safety and health of work on construction projects.
Work accidents and occupational diseases caused by workers must be prevented even if they can be completely eliminated. In overcoming these problems, the government has issued laws and various regulations concerning occupational safety and health (OHS). But all government efforts will not succeed without a response from companies engaged in construction. The existence of a paradigm of safety construction that is considered to only make the value of the project expensive that is not entirely correct, if examined further because the costs incurred for an accident is far more fantastic than the costs incurred for the procurement of safety equipment.

Legal Basis
In this chapter the author will discuss the results of data evaluation to obtain answers to this study based on the data that has been obtained and the results of the field, namely observations and interviews with respondents who understand and are responsible in their fields related to the implementation of SMK3 and the preparation of their costs on the project. Then a discussion about the results obtained.
The basis for evaluating and making interview forms is from previous research based on Peraturan Menteri Pekerjaan [1-2].
Peraturan Menteri Pekerjaan [1]
About the Guidelines for the Occupational Safety and Health Management System (SMK3) in the Field of Public Works Construction
[2] Concerning the Cost of Implementing Occupational Safety and Health Management System (SMK3) in the Field of Public Works, which is to regulate the details of the application of SMK3 in the Peraturan Menteri Pekerjaan [1]
Interview Data
In this study, the results obtained after data collection and data processing will be elaborated, namely by interviewing and evaluating the SMK3 Cost Budget Plan (RAB). The format of the interview form is shown in Figure 1 below:



Figure 1: Interview Form’s From Previous Case Study
In making interview questions here the writer guides the previous research entitled "Evaluasi Penerapan Biaya Keselamatan dan Kesehatan Kerja (K3) dalam Proyek APBD Tingkat II” " whose contents cover or are based on [1-2]
Discussion of the result of the interview
As explained earlier, the author conducted an interview with the Respondent namely Safety Officer Hutama Karya (HK) with questions as stated in the interview form and after that analyzed using 3 data analysis namely: Data Reduction, Data Display and then Conclusion / Verification. The following are conclusions from the results of the interviews conducted:
Safety officer / staff responsible for K3 understands and is aware of [1,2]
The cost of implementing SMK3 is taken by the contractor at 0.27% of the total cost.
There is a work safety and health plan (K3K3) document on the project.
The contractor does not yet have a special OHS staff in the project.
The contractor has implemented K3 as stated in [1,2]
The following is a comparison between existing policies in the regulations and those implemented in the field, which can be seen in Figure 2:

Figure 2: Comparison of Government Regulations and Those in the Field
In the Bendo - Ponorogo dam project as explained above, the contractor does not include SMK3 costs into general costs, but the SMK3 costs are taken from the Environmental Costs. Even though the contractor did not include the SMK3 costs into general costs, the Contractor continued to make detailed Budget Design or (RAB) for the application of SMK3 in the field. Costs used for SMK3 are taken at 0.27% by the contractor from the contract cost.
Budget for the implementation of PPE on the construction of Main Dam
After knowing the Budget Design of SMK3 cost for Bendo Ponorogo reservoir construction project where the cost taken for SMK3 needs is 0.27% of the contract value. The author tries to make a tabulation to find the amount of costs for the needs of Personal Protective Equipment (PPE) constructed the Dam Dam ponorogo reservoir project. Before making tabulation the following are the types of jobs that exist in the main dam taken from Curva S AMD XIII can be seen on Table 1.
Table 1: Recapitulation of Main Dam Construction Works

And the following is a Tipical Cross section of the main dam construction Bendo - Ponorogo Dam Project can show in Figure 4 below :

Figure 3: Tripical Cross Section of Main Dam
Recapitulation of PPE Cost Budget at Main Dam
After making tabulations and calculating the cost of personal protective equipment (PPE) used in every Main Dam construction work, shown in Table 3, the following is a recapitulation of the results of each tabulation:
Table 2: Work Tabulation Recapitulations in Main Dam

And the following is the recapitulation of the Personal Protective Equipment Budget (APD) of each existing work constructed Main Dam, shown in Table 4 below:
Table 3: Recapitulation of PPE Costs at Main Dam
No. | Activities | cost |
1 | Cleaning and Stripping | IDR 7,210,000.00 |
2 | Ordinary land work excavation | IDR 6,180,000.00 |
3 | Hardrock excavation (mechanic) | IDR 8,240,000.00 |
4 | Core stockpile(Zone 1) | IDR 12,360,000.00 |
5 | Core stockpile (Zone 2 ) | IDR 8,240,000.00 |
6 | Random Stockpile (Zone 3) | IDR 26,265,000.00 |
7 | Stone Pile work (Zone 4 ) | IDR 18,540,000.00 |
8 | Rip-Rap stockpile (Zone 5) | IDR 12,360,000 |
9 | Drilling and Grouting | IDR 2,575,000 |
10 | Mechanic, Assistant & Helper | IDR 4,120,000 |
The conclusions obtained from this research are as follows:
The implementation of occupational Health and safety (OHS) in the construction of the Bendo-Ponorogo Dam Project has been carried out by the contractor but has not been maximized. Because there are still some terms and conditions of ministerial regulations that have not been implemented by the contractor.
For the implementation of Occupational Health and Safety (OHS) the contractor takes 0.27% of the total contract value and for PPE needs only the construction of Main Dam is Rp. 106,090,000.00. Of course the amount is still normal because the costs to be incurred for an accident are far more fantastic than the costs incurred for the procurement of safety equipment.
Acknowledgement
The author would like to show our gratitude to our lecturers and supervisors for their ceaseless mental support, expertise and concise supervisors or advices during this research.
The authors declare that they have no conflict of interest
No funding sources
The study was approved by the Universitas Muhammadiyah Surakarta.